renovation

Renovation Update February 24, 2024

Another Renovation Update – Construction begins in March!

  • Demolition is scheduled to begin the first week of March! With the exception of the roofs, we hope to have most of the project completed by July! Availability of supplies and lead time on items like the lift (elevator) will impact some of the timing. 

  • The demolition, asbestos abatement, and installation of new flooring, carpentry, etc. is being phased by area to attempt to ensure the least amount of disruption possible. 

  • Staff are beginning to reach out to impacted ministries as the timeline becomes clear. 

  • Our number one priority is to keep handicap accessibility to the sanctuary on Sundays throughout the project. 

Questions? Reach out to a committee member to chat: Terrie S, the Rev. Bingham Powell, Flossie B, or Louise Fortuna.

Renovation Update February 7, 2024

Main Level Renovation project continues to move ahead. Some of the milestones met and upcoming are listed below.

  •  The Guaranteed Maximum Price (GMP) contract has been submitted to St. Mary’s and signed off on

  • Construction permit obtained for the project

  • The sub-contractors are in the process of ordering materials and obtaining timelines for their delivery

  • McKenzie Commercial is putting together the project time line and once the lead time on material and equipment is obtained, they will be working with St. Mary’s remodel committee to determine the best timing and least disruptive way to begin demolition.

Feel free to contact any of remodel committee with any questions; Flossie B, Louise F, Bingham+ and Terrie S.

Renovation Update November 12, 2023

Now that we have successfully completed our fundraising, we are getting close to the start of construction. We do not have a schedule yet; the contractor is working on that. 

From this point forward, expect regular updates on progress as we get closer to construction. Here are a few updates: 

To read the update, click “Read More.”